Since Hitachi began the development of nuclear technologies in 1957, it has been involved with a number of nuclear projects, including research reactors, export and development reactors, and commercial reactors.

Start of operation

1957
  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Research Reactor (JRR-1) (auxiliary facility)
  • Output : 0.05MWt
  • Type : Research reactor
1960
  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Research Reactor (JRR-2) (helium purification system)
  • Output : 10MWt
  • Type : Research reactor
1961
  • Delivery customer : Hitachi, Ltd. Central Research Laboratory
  • Plant name (delivered facilities) : Research Reactor (HTR) (complete set of nuclear reactor equipment)
  • Output : 0.1MWt
  • Type : Research reactor

1962

  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Research Reactor (JRR-3) (main reactor, other equipment)
  • Output : 10MWt
  • Type : Research reactor
1963
  • Delivery customer : Musashi Institute of Technology
  • Plant name (delivered facilities) : Research Reactor (TRIGA reactor) (complete set of nuclear reactor equipment)
  • Output : 0.1MWt
  • Type : Research reactor

 

  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Japan Power Demonstration Reactor (JPDR) (reactor system equipment)
  • Output : 12.5MWe
  • Type : Research reactor
1964
  • Delivery customer : Kyoto University
  • Plant name (delivered facilities) : Research Reactor (KUR) (complete set of nuclear reactor equipment)
  • Output : 1MWt
  • Type : Research reactor
1965
  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Research Reactor (JRR-4) (complete set of nuclear reactor equipment)
  • Output : 1MWt
  • Type : Research reactor

1968

  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : Materials testing reactor (JMTR) (reactor core structure, other equipment)
  • Output : 50MWt
  • Type : Research reactor

1970

  • Delivery customer : The Japan Atomic Power Company
  • Plant name (delivered facilities) : Tsuruga-1 Nuclear Power Plant (nuclear reactor pressure vessel, core structure, other equipment)
  • Output : 357MWe
  • Type : Commercial reactor
1971
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Fukushima Daiichi Nuclear Power Plant Unit 1(nuclear reactor containment vessel, other equipment)
  • Output : 460MWe
  • Type : Commercial reactor
1972
  • Delivery customer : Government of Pakistan
  • Plant name (delivered facilities) : Karachi Nuclear Power Plant (turbines, generators)
  • Output : 137MWe
  • Type : Export
1974
  • Delivery customer : Chugoku Electric Power Company
  • Plant name (delivered facilities) : Shimane Nuclear Power Station Unit 1 (complete set of plant equipment)
  • Output : 460MWe
  • Type : Commercial reactor
1976
  • Delivery customer : Chubu Electric Power Co., Inc.
  • Plant name (delivered facilities) : Hamaoka Nuclear Power Station Unit 1 (set of turbine equipment)
  • Output : 540MWe
  • Type : Commercial reactor
1977
  • Delivery customer : Power Reactor and Nuclear Fuel Development Corporation (nuclear reactor equipment, other equipment)
  • Plant name (delivered facilities) : Fast Breeder Reactor "Joyo" (nuclear reactor equipment, other equipment)
  • Output : 50MWt
  • Type : Development reactor
1978
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Fukushima Daiichi Nuclear Power Station Unit 4 (complete set of plant equipment)
  • Output : 784MWe
  • Type : Commercial reactor

 

  • Delivery customer : The Japan Atomic Power Company
  • Plant name (delivered facilities) : Tokai No. 2 Power Station (nuclear reactor equipment, turbine auxiliary equipment, other equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor

 

  • Delivery customer : Chubu Electric Power Co., Inc.
  • Plant name (delivered facilities) : Hamaoka Nuclear Power Station Unit 2 (set of turbine equipment)
  • Output : 840MWe
  • Type : Commercial reactor

 

  • Delivery customer : Power Reactor and Nuclear Fuel Development Corporation
  • Plant name (delivered facilities) : Advanced thermal reactor "Fugen" (nuclear reactor equipment)
  • Output : 165MWe
  • Type : Development reactor

 

  • Delivery customer : Taiwan Power Company
  • Plant name (delivered facilities) : Jinshan Nuclear Power Plant Unit 1 (nuclear reactor containment vessel)
  • Output : 636MWe
  • Type : Export
  • 1979
  • Delivery customer : Taiwan Power Company
  • Plant name (delivered facilities) : Jinshan Nuclear Power Plant Unit 2 (nuclear reactor containment vessel)
  • Output : 636MWe
  • Type : Export

1984

  • Delivery customer : Kernkraftwerk Leibstadt (Switzerland)
  • Plant name (delivered facilities) : Nuclear Power Plant Leibstadt (interior reactor structure)
  • Output : 1,220MWe
  • Type : Export

 

  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Fukushima Daini Nuclear Power Station Unit 2 (complete set of plant equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor
1986
  • Delivery customer : Public Service Electric and Gas Company (US)
  • Plant name (delivered facilities) : Hope Creek Generating Station, Unit 1 (nuclear reactor pressure vessel)
  • Output : 1,117MWe
  • Type : Export
1987
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Fukushima Daini Nuclear Power Station Unit 4 (complete set of plant equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor

 

  • Delivery customer : Chubu Electric Power Co., Inc.
  • Plant name (delivered facilities) : Hamaoka Nuclear Power Station Unit 3 (set of turbine equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor
1989
  • Delivery customer : Chugoku Electric Power Company
  • Plant name (delivered facilities) : Shimane Nuclear Power Station Unit 2 (complete set of plant equipment)
  • Output : 820MWe
  • Type : Commercial reactor
1990
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Kashiwazaki-Kariwa Nuclear Power Station Unit 5 (complete set of plant equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor
1993
  • Delivery customer : Chubu Electric Power Co., Inc.
  • Plant name (delivered facilities) : Hamaoka Nuclear Power Station Unit 4 (set of turbine equipment)
  • Output : 1,137MWe
  • Type : Commercial reactor

 

  • Delivery customer : Hokuriku Electric Power Company
  • Plant name (delivered facilities) : Shika Nuclear Power Plant Unit 1 (complete set of plant equipment)
  • Output : 540MWe
  • Type : Commercial reactor
1994
  • Delivery customer : Power Reactor and Nuclear Fuel Development Corporation
  • Plant name (delivered facilities) : Fast Breeder Reactor "Monju" (intermediate heat exchange equipment, steam generator equipment, other equipment)
  • Output : 280MWe
  • Type : Development reactor

 

  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Kashiwazaki-Kariwa Nuclear Power Station Unit 4 (complete set of plant equipment)
  • Output : 1,100MWe
  • Type : Commercial reactor
1996
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Kashiwazaki-Kariwa Nuclear Power Station Unit 6 (set of turbine equipment)
  • Output : 1,356MWe
  • Type : Commercial reactor
1997
  • Delivery customer : Tokyo Electric Power Company
  • Plant name (delivered facilities) : Kashiwazaki-Kariwa Nuclear Power Station Unit 7 (set of nuclear reactor equipment)
  • Output : 1,356MWe
  • Type : Commercial reactor
1998
  • Delivery customer : Japan Atomic Energy Research Institute
  • Plant name (delivered facilities) : High Temperature Engineering Test Reactor (nuclear reactor pressure vessel, other equipment)
  • Output : 30MWt
  • Type : Research reactor
2002
  • Delivery customer : Tohoku Electric Power Company
  • Plant name (delivered facilities) : Onagawa Nuclear Power Station Unit 3 (set of turbine equipment)
  • Output : 825MWe
  • Type : Commercial reactor
2005
  • Delivery customer : Chubu Electric Power Co., Inc.
  • Plant name (delivered facilities) : Hamaoka Nuclear Power Station Unit 5 (set of turbine equipment)
  • Output : 1,380MWe
  • Type : Commercial reactor
2006
  • Delivery customer : Hokuriku Electric Power Company
  • Plant name (delivered facilities) : Shika Nuclear Power Plant Unit 2 (complete set of plant equipment)
  • Output : 1,358MWe
  • Type : Commercial reactor
  • [Unit descriptions] Wt: thermal output, We: electrical output, 1 MW = 1,000 kW
  • Note: Includes some plants worked on a partial basis. For research reactors and development reactors, the starting year of operation is the year of first critical state, and output is the initial rated value.
  • [Sources] Commercial reactors: Trends in Global Nuclear Power Development (Japan Atomic Industrial Forum), Research reactors and development reactors: Public materials from each research and development organization, websites, etc.